Roof on, brickwork up, services in, and the last look before the linings.
The Leppington lock-up findings run to the envelope and the services together. Weep holes never formed. Ducting resting on the ceiling frame rather than suspended, which crushes the run and kills the airflow the system was designed around. Sarking and wall wrap detail. Stormwater with insufficient cover. Temporary downpipes not installed, so the roof drains onto the ground beside a fresh slab. And the termite management notice missing from the meter box where it should already be.

Annotated findings from Lock-up (pre-plaster) inspections on Leppington builds. Client addresses withheld.




1Bored piersAfter boring and cage placement, before concrete
2Slab pre-pourThe day before the pour, steel and formwork complete
3FrameOnce frame and trusses are up and the roof is on, before lining
5FixingAfter mouldings, doors and joinery, before the painter
6WaterproofingAfter the membrane is applied and before any tile is laid
7Pre-handover (PCI)Two to three weeks before your handover dateInstant online pricing, or talk to the booking team on 1300 471 805.
Flexible duct resting on ceiling joists gets crushed and kinked, and a crushed duct moves a fraction of the air it was sized for. The room at the end of it never heats properly and the cause sits above a finished ceiling.
To take roof water away during construction. Without it, every rain event dumps the whole roof beside your new slab, which is exactly where you least want saturated ground.
They are. What defines the stage is services in and linings not, which here lasts a few days.
Every one, marked fixed, partly fixed or outstanding.
Roughly two hours on site, plus writing, and more on a bigger or two storey house.
We examine what remains open and record the areas already sealed.